Road construction


The history of road construction

The methods of constructing roads have changed a lot since the first roads were built around 4,000 BC – made of stone and timber. The first Roman roads were stone paved, built in North Africa and Europe for military operationsRoad construction techniques were gradually improved by the study of road trafficstone thickness, road alignment, and slope gradients, developing to use stones that were laid in a regular, compact design, and covered with smaller stones to produce a solid layer

Modern road construction

Modern roads tend to be constructed using asphalt and/or concrete.

Very broadly, the construction of roads includes three processes:

§  Setting out.

§  Earthworks.

§  Paving construction.

This is carried out following the dimensions specified in layout drawings.

A commonly used setting out procedure is the profile board method. A series of boards that show the exact level 1 metre above the completed construction level are placed at intervals along the proposed line of the road. A profile board with a fixed height, called the traveller, is used for controlling the excavated levels between these profile boards. By placing the traveller in the sight-line between two level boards, it can be seen whether or not the excavation has been carried out to correct levels and adjusted accordingly. The level of each profile board is controlled using a line level which is a short spirit level hung from a nylon string. The line operator moves the string up or down until the bubble is centred. Junctions, hammer heads, turning bays and intersecting curves can be laid out in a similar manner.

Earthworks involve the removal of topsoil, along with any vegetation, before scraping and grading the area to the finished ‘formation level’. This is usually done using a tractor shovelgrader or bulldozer. Below the formation level, the soil is known as the ‘subgrade’. It is essential that the strength of the subgrade is tested prior to earthworks beginning.

Most earthworks are formed by cut-and-fill, and the type of ‘fill’ material must be considered, not only in terms of its physical properties, but on the conditions in which it is to be used, and the methods of compaction.

Depending on its quality, compressible subsoil may be removed or stabilised. If the cost of full or partial excavation of subsoil is uneconomical and would be likely to result in consolidationsand wicks or sand drains may be used. Sand wicks are sand-filled boreholes beneath the road embankment that give greater stability to the soil by decreasing the length that water has to travel in a drainage path, so dissipating water pressureSand drains alongside the road are used to intercept ground water. Subsoil drainage should be provided to deal with seepage through pavements and verges, from higher ground and a result of the seasonal rise and fall of the water table.

Subgrade strength

The required thickness of the pavement is determined by the subgrade strength, so it is desirable to make the subgrade as strong as possible.

The strength of the subgrade can be achieved by using the following techniques:

§  Removal of poor material in cuttings and replacing with selected fill.

§  Compacting subgrade to a high dry density.

§  Providing adequate subsoil drainage.

§  Soil stabilisation methods such as the use of cement, bituminous materials or chemicals.

Subgrade strength will decrease as moisture content increases so protection may be required if it is to left exposed for any length of time. Protection covering can be either:

§  Medium gauge plastic sheeting with 300 mm laps.

§  Sprayed bituminous binder with a sand topping.

Once the subgrade has been prepared and drainage or buried services installed, the paving construction can begin. Paving can be either flexible or rigid. There are pros and cons to each type, with one being selected over the other depending on the specific needs of a project.

Rigid pavements tend to have lower maintenance costs, a longer design life and higher flexural strength; but flexible pavements tend to have lower construction costs and a better ability to expand and contract with temperature and so do not need expansion joints.

Flexible paving

Flexible paving consists of materials applied in layers directly over the subgrade onto which the traffic loads are distributed. To prevent permanent deformation, and therefore an uneven running surface, the thicknesses of individual layers must be capable of distributing such loads. The subgrade is compacted with the sub-base on top of it. On top of this the surfacing is laid which is made up of the base layer and the wearing course.

Surfacing

The wearing course is the upper layer of bituminous material, often denser and stronger than the base layer. The thickness depends on the material specification and the amount of wear that is expected. Desired properties are good non-skid capabilities, minimal glare and acceptable durability. The main materials that are used are hot rolled asphalt (HRA), dense bitumen macadam (DBM), dense tar macadam (DTM) and porous asphalt (PA). Porous asphalt is especially suitable as it is an open-graded material that is designed to allow rapid drainage of surface water, thereby reducing spray as well as tyre noise. The base will typically have a minimum thickness of 60 mm and is usually made of dense bitumen macadam or asphalt. It is laid with the appropriate cross falls and gradients.

Sub-base

This is placed in a layer usually not exceeding 150 mm over the subgrade after waterproofing is complete. Various materials can be used but it is common for crushed stone or dry lean concrete (such as 1:15) laid and compacted by heavy rollersCellular Concrete (Foamed Concrete) is another material that can be used for the sub-base, the thickness and strength required depends upon the type of road.

Rigid paving

Rigid paving consists of a reinforced or unreinforced insitu concrete laid over a thin granular base. The rigidity and strength of the pavement enables the loads and stresses to be distributed over a wide area of the subgrade.

Rigid paving is typically made up of the following layers (from bottom to top):

§  Subgrade.

§  Sub-base of thick crushed stone. Usually to a thickness of 80 mm.

§  Anti-friction membrane normally made of polythene sheeting. This also prevents grout loss from the freshly laid concrete.

§  Insitu concrete paving slabReinforcement in the form of either steel fabric or re-bar may be used.

§  Asphalt or similar topping if required.

Longitudinal and transverse joints are required in rigid paving between the slabs, limiting the stresses applied due to subgrade restraint (friction between the pavement and subgrade), and providing room for expansion and contraction movements. The spacing of road joints is determined by:

§  The hickness of the slab.

§  Whether there is reinforcement in the slab or not.

§  The expected traffic load and flow rate.

§  The temperature at which the concrete is laid.

For more information, see

§  Road joints.

§  Highway drainage.

§  Kerbs.

 


Comments

Popular posts from this blog

Traffic Engineering Design Process

9 Elements for Designing Your Ideal Bathroom: A Practical Guide for Function and Style